HVAC work of Ducting and Cassette units installed at a restaurant in Gurgaon, India. The site has been completed under the direction of a High Repute Architect. This is a Modern Contemporary Design, where the Ductwork is visible and no false ceiling has been installed.
Duct Work
The Duct work has been completed in 3 Weeks time, the duct have been connected through a AHU ( Air Handling Unit), the total Tonnage is 44 Tr, this being supplied heat exchange through a Chill Water System, There are VFD ( Variable Flow Damper) for air balancing.
Additional Cassette Units
During Peak Summer season, when the outside temperature is above 40 degrees, and especially when the inside of the restaurant is at its peak capacity, the inside temperatures tends to cross 30 degrees, for this we had 3 additional cassette units of 4Tr installed to manage the problem.